DraMS Consumables
Post processing softare measures consumable items such as WRP run time, HCV cycles, etc.
How each of the DraMS consummables is tracked.
WRP
WRP run-time Run-time is calculated by measuring from the time the WRP speed exceeds 5400 RPM unt...
HCV
HCV Cycles One cycle of the hCV include an HCV open and an HCV close. An HCV open is defined by c...
Filaments
DraMS has two filaments, filament A and filament B. On Time Filament A and Filament B on time are...
Detectors (aka EMs)
On Time EM A and EM B on times are determined by summing the on times for all scans, and then loo...
Laser
Laser Shots Laser shots are determined by summing the number of pulses in the LEU.MAX_HKHS packet...
GPS Valves
GPS Valve Cycles GPS valves are the microvalves and GC valves in the manifolds. The high- conduct...
Multifunction Valves
MFV Cycles Counts the number of times the Multifuntion Valve (MFV) has been opened. A cycle consi...